向家坝右岸电站发电机定子机座分5瓣在现场组装,对定子机座组装过程中的组圆、定子测圆架安装、定位筋安装等施工工艺和技术要求进行详细介绍,为巨型水轮发电机定子机座组装提供参考。
The stator frame of hydro-generator in right-bank power plant of Xiangjiaba Hydropower Station is divided into five segments and assembled in field. The processes and technologies for five segments' assembly, roundness measurement device installation and positioning rib installation are introduced in detail herein. These processes and technologies can provide reference to the stator frame assembly of giant hydro-generators.
出处
《水力发电》
北大核心
2014年第1期14-16,33,共4页
Water Power
关键词
定子机座
组装
测圆架
定位筋
向家坝水电站
stator frame
assembly
roundness measurement device
positioning rib
Xiangjiaba Hydropower Station