摘要
向家坝右岸500kV GIS配电装置的安装包括9个断路器间隔、相应母线及出线套管、设备支架等附属设备的运输、检查、安装、电气连接,设备接地端子与电站接地网的连接,设备的调试、现场试验和试运行等工作。对向家坝右岸500kV GIS安装的施工准备、安装重点、常规试验以及在安装过程中出现的问题进行了介绍,并针对问题采取了处理措施。
The installation engineering of 500 kV GIS for the fight-bank power plant of Xiangjiaba Hydropower Station includes the transport, inspection, installation and electrical connection of nine breaker compartments, busbars and bushings, supporting and other ancillary equipments, the connections of equipment grounding terminal to plant grounding net, and the field test and commissioning of equipments. The construction preparation, installation focuses routine tests and problems in the installation of 500kV GIS are introduced, and the treatment measures for solving these problems are also presented.
出处
《水力发电》
北大核心
2014年第1期49-52,共4页
Water Power
关键词
GIS
安装
监理
向家坝水电站
GIS
installation
supervision
Xianghiaba Hydropower Station