照壁山隧道出口碎屑流地层围岩加固处理技术

On surrounding rock consolidation technique for debris flow layer at Zhaobi Mountain's tunnel exit
下载PDF
导出
摘要 结合工程实践,介绍了在照壁山隧道施工中遇到碎屑流地层时对围岩的加固处理技术,通过后期施工实践证明采取的加固措施取得了很好的效果,为同类工程施工提供了参考。 Combining with the engineering practice, the paper introduces the consolidation technique for the surrounding rock in the tunnel con struction of Zhaobi Mountain, proves the consolidation measure has better effect by the construction practice at later period, so as to provide some reference for similar projects.
作者 张玉浩
出处 《山西建筑》 2014年第4期156-157,共2页 Shanxi Architecture
关键词 碎屑流地层 围岩加固 注浆 管棚支护 debris flow layer, surrounding rock consolidation, grouting, pipe-shed support
  • 相关文献

参考文献2

二级参考文献4

  • 1[4]Thomas Dickmann,Rata Awasthi. The Tunnel Seismic Prediction Method and its Impact on Logistic Optimisation in Tunnelling. Proceedings of the International Conference on Rock Engineering Techniques for Site Characterisation, Bangalore, India,Dec. 1999, 6~8.
  • 2[5]Xiao Shuan, Sattel G. Advance seismic prediction in tunnel construction-a new TSP surveying system in use in the Vereina Tunnel, Switzerland. Presented by International Symposium on New Development in Rock Mechanics and Engineering, Shenyang, P. R.China, Oct 1994.
  • 3赵勇,肖书安,刘志刚.TSP超前地质预报系统在隧道工程中的应用[J].铁道建筑技术,2003(5):18-22. 被引量:59
  • 4温树林,吴世林.TSP203在云南元磨高速公路隧道超前地质预报中的应用[J].地球物理学进展,2003,18(3):465-471. 被引量:79

共引文献122

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部