基于全寿命周期成本的变电站设备检修模糊规划模型 被引量:40

A Fuzzy Programming Model Based on Life Cycle Cost for Equipment Maintenance in Substations
下载PDF
导出
摘要 变电站的设备检修工作不仅是保障变电站正常运行的基础,也是降低变电站全寿命周期成本(LCC),实现效用与成本相互平衡的重要途径。文中首先基于模糊时间序列法,对电气设备在寿命周期内的可靠性参数进行模糊预测,接着引入役龄回退理论,以设备LCC中检修成本和故障成本最小化为目标,建立了检修策略的优化决策模型,并运用模糊规划理论实现了模型的求解。实例应用结果显示,提出的模糊规划模型可以为变电站电气设备检修策略的制定以及变电站的全寿命周期管理提供有益参考。 Equipment maintenance in substations is the basis of normal operation as well as an important channel through which to reduce the life-cycle cost(LCC)and realize balance between the utility and the cost.Firstly,on the basis of fuzzy time series,a fuzzy prediction is made of the reliability parameters of electrical equipment in the whole life cycle.Secondly,the age reduction theory is introduced.And with minimum equipment maintenance cost and failure cost of LCC as the objective,an optimization decision model for maintenance strategy is developed.Finally,the fuzzy programming theory is used to solve the model.The application example shows that the fuzzy programming model proposed can provide valuable reference for the formulation of equipment maintenance strategy and life-cycle management in substations.
出处 《电力系统自动化》 EI CSCD 北大核心 2014年第1期44-50,共7页 Automation of Electric Power Systems
关键词 变电站设备 检修策略 全寿命周期成本 模糊时间序列 役龄回退 模糊规划 equipment in substations maintenance strategy life-cycle cost(LCC) fuzzy time series age reduction fuzzy programming
  • 相关文献

参考文献13

二级参考文献48

共引文献237

同被引文献378

引证文献40

二级引证文献254

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部