摘要
以秦山第二核电厂1、2号机组和田湾核电厂1、2号机组为例,对国内已运行的压水堆核电厂在调试阶段进行安全壳喷淋试验时所采用的两种方式进行了比较分析,总结出两种喷淋试验方法各自的优缺点,可为国内新建核电机组的安全壳喷淋系统的调试试验提供借鉴。
In this article,two commissioning test methods for the containment spray system of the domestic PWR were compared during the commissioning phase,taking unit 1,2 in Qinshan Phase ⅡNPP and unit 1,2 in Tianwan NPP for example. The advantages and disadvantages of the two methods were summarized and can be used for the commissioning test methods of new constructing nuclear power plants as reference.
出处
《核安全》
2013年第4期89-91,共3页
Nuclear Safety
基金
核电厂安全监管运行执照文件规范化研究(201009031)
关键词
安全壳喷淋系统
调试试验
压水堆核电厂
containment spray system
commissioning test
pressurized water reactor plant