高大墩柱模板托架施工设计

Tall pier template bracket construction design
下载PDF
导出
摘要 高大墩柱施工时如果施工脚手架从地面搭起,随着架体的增高,架体承受的竖向荷载及风荷载越来越大,架体的安全系数逐渐降低。故我们对高大墩柱施工的架体进行改进,在墩柱钢模板上增加脚手架托架,更好的保证了墩柱施工的质量、施工进度和安全,同时节省大量脚手架。 Tall pier construction,if the construction scaffolding erected from the ground,along with the increase of the body frame,the frame body to withstand the vertical loads and wind loads will be increasing,the safety factor of the frame body will gradually decrease. So the frame body of tall pier construction has been improved,increasing the pier steel scaffolding board bay that ensures better quality of pier construction projects, construction progress and security,and at the same time saving a lot of the erection and construction of scaffolding, reducing the amount of labor workers.
出处 《科技创新导报》 2013年第30期77-78,共2页 Science and Technology Innovation Herald
关键词 高大桥墩 模板托架 施工设计 High-brage pier Template bracket Construction design
  • 相关文献

参考文献2

  • 1建筑施工扣件式钢管脚手架安全技术规范(JGJ130~2011)[S].
  • 2建筑施工计算手册[M].中国建筑工业出版社,2007,7.

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部