摘要
盾构施工常会遇到各种障碍物。以上海轨道交通7号线北延伸段陆翔路站—潘广路站区间隧道工程为背景,从盾构设备改造、盾构推进控制、施工监测等方面介绍了盾构切削钢筋混凝土桩穿越厂房所采取的技术措施,对同类工程施工具有参考价值。
Tunnel shielding often meets many obstacles. Based on the tunneling project of Shanghai metro Line 7 north extension section, the shielding technology applied in cutting steel reinforced concrete piles is introduced, inclu- ding the manufacture of tunnel shield, the control of shiel- ding and supervision of the engineering, the experiences are summarized for other tunneling projects in China.
出处
《城市轨道交通研究》
北大核心
2014年第1期99-102,共4页
Urban Mass Transit
关键词
盾构
切削桩基
施工技术
tunnel shield
cutting pile
construction tech-nology