主被动联合支护在大断面硐室破碎围岩加固中的应用 被引量:3

Application of Active-passive Combined Supporting Technology in Crushing Surrounding Rock Reinforcement of Large Section Chamber
下载PDF
导出
摘要 针对中马村矿39泵房断面大、围岩破碎、频繁破坏返修的情况,结合地质条件和围岩表面及深部破坏特征,分析了硐室变形破坏机理,提出了锚网索一次支护+二次U型钢封闭支架刚性支护+三次喷射混凝土+注浆加固并浇筑混凝土反拱联合支护技术,并在39泵房实施应用,取得了良好的效果。 According to the status quo of large section,fractured surrounding rock and frequent failure of repair in 39 pump room of Zhongmacun Coal Mine,combined with the geological condition and surface and deep failure features of surrounding rock,the deforma- tion and failure mechanism of the chamber were analysed, a combined supporting technology was proposed,which contains bolt-mesh-ca- ble supporting firstly + U Steel closed bracket rigid supporting secondly + three times of sprayed concrete + grouting reinforcement and concrete pouring of inverted arch. This technology was applied in 39 pump room, and has achieved good results.
出处 《中州煤炭》 2014年第1期4-7,共4页 Zhongzhou Coal
关键词 大断面 泵房 复合支护 注浆 large section pump room combined supporting grouting
  • 相关文献

参考文献13

二级参考文献81

共引文献1197

同被引文献19

引证文献3

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部