期刊文献+

阳洞滩2号隧道特大涌泥塌方处治方案研究 被引量:3

Treatment of Collapse and Mud Accident in Yang Dong Tan No.2 Tunnel
下载PDF
导出
摘要 阳洞滩2号隧道为双洞单向交通隧道。隧道施工过程中出现了隧道塌方。借助数值分析技术,结合数值模拟,仿真分析隧道塌方抢险的力学效应,进而形成阳洞滩2号隧道右洞YK194+040-YK194+085段处理方案。为隧道的安全施工提供了技术保障。 Yang Dong Tan No. 2 tunnel is for two hole one-way traffic tunnels. The tunnel collapse happen during its construction. By using the numerical analysis technology, combined with numerical simulation, the simulation analysis of mechanical effect of tunnel collapse rescue is made in this paper. Later the positive hole beach No. 2 tunnel right hole YKI94 + 040 - YK194 + 085 segment processing scheme is formed . It will provide the technical support for the construction safety of tunnel.
出处 《公路工程》 北大核心 2013年第6期17-19,42,共4页 Highway Engineering
基金 湖南省交通运输厅科技项目(200924)
关键词 隧道塌方 数值模拟 抢险方案 技术支持 tunnel collapse numerical simulation rescure scheme technical support
  • 相关文献

参考文献2

  • 1李圆圆.大跨度隧道施工力学响应及地表沉陷预计[D]{H}长沙:中南大学,20085.
  • 2向俊宇.大跨度隧道监控量测及动态反馈信息化施工技术研究[D]{H}长沙:中南大学,20095.

同被引文献115

引证文献3

二级引证文献196

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部