由于地基的瞬时沉降发生的时间短、速率大 ,极易引起过大的不均匀沉降。本文分析一工程实例 ,说明在深基坑施工降水时 ,瞬时沉降所产生的影响。
Due to the short time occurrence of instantanous settlement,it will usually induced excessive uneven settlement on neighboring buildings.In this paper,a practical example is analysed to show the effect of instantanous settlment induced by dewatering of a deep foundation pit construction.
出处
《土工基础》
2000年第4期38-40,共3页
Soil Engineering and Foundation
关键词
建筑物
深基础
工程施工
瞬时沉降
dewatering,instantanous settlement,deep foundation pit