摘要 鉴于500 kV断路器不能快速切除故障将存在直流换相失败的风险,二次系统必须满足"N-1"要求。阐述了某500 kV断路器机构控制回路的原理和不足,结合现场对其双重化改造进行分析,并提出了施工改造调试过程中的注意事项。建议在新投或者技改工程中,对断路器厂家严格要求其第一、二路分闸回路在电气方面的独立性,保障电网的安全稳定运行。 There exists the risk of DC commutation failure because a 500 kV circuit breaker is unable to eliminate fault fast, so the secondary system has to meet the "N-1" requirements. This paper expatiated on the principle and insufficiency of certain 500 kV circuit-breaker machine control circuit and combined with on-site condition to analyze and to discuss its double transformation in depth. The raised caution items in the process of construction transformation debugging provided references for fellow traders. This paper suggested that in the process of new bidding project or technique reforming project, the enterprise of circuit breakers should be strictly required to be independent of primary and secondary breaking circuits in electrical aspect, so as to ensure safe and stable operation of grid.
出处 《电工电气》 2014年第1期33-36,共4页 Electrotechnics Electric
关键词 断路器 控制回路 双重化改造 调试 circuit breaker control circuit double transformation debugging
  • 相关文献

参考文献2

二级参考文献2

  • 1中华人民共和国能源部.继电保护和安全自动装置技术规程[M].北京:中国标准出版社,2006.
  • 2广东省电力系统继电保护反事故措施及释义(2007版)[M].北京:中国电力出版社,2008.

共引文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部