摘要 提出了从网络环境入手,解决无关的网络报文、组播报文的全站广播等问题,对网络报文的传输进行有序的管理,提高网络传输质量,大大减轻测控装置端口的压力。通过更换现有的主交换机和级联交换机实现VLAN的划分和静态组播管理,减少测控装置端口上的报文信息,达到消除通信问题的目的。 The problems of independent network packet, broadcast of multicast packets and other issues are solved based on network environment. The package transmission of the network is managed, which improves the network transmission quality and greatly reduces the monitoring device port pressure. By replacing the existing master switch and cascading switch- es, the VPN division and static multicast management are implemented. The packets on the monitor and control ports are re- duced and communication problems are eliminated.
作者 欧阳启建
机构地区 佛山供电局
出处 《自动化应用》 2013年第12期103-105,共3页 Automation Application
关键词 通信中断 处理方案 VLAN划分 静态组播管理 交换机 评估 communication interruption treatment scheme VLAN division static multicast management switch assess-ment
  • 相关文献

参考文献2

二级参考文献9

共引文献66

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部