摘要
结合沈阳市浑南新区现代有轨电车一期工程,通过对有轨电车转向架检修间的设计中转向架各部件的检修进行详细论述,介绍转向架检修间流水线设计的基本情况,并对转向架检修之后的标准及检修流程、各部件的检修进行说明,指出可能存在的不尽合理之处。
Maintenance of bogie components of modern trams is illustrated in detail with the first-period modern trams project in Hunnan New District,Shenyang as the background.Assembly line design of bogie maintenance depot is introduced,and the specification of repaired bogie is illuminated.Shortcomings in design particulars are pointed out.
出处
《都市快轨交通》
北大核心
2013年第6期197-200,共4页
Urban Rapid Rail Transit
关键词
有轨电车
转向架
检修
modern tram
bogie
maintenance