摘要
文章主要介绍了包钢新体系300万t焦化项目1#焦炉工程焦炉顶板埋管安装施工工艺和方法,改进了埋管的固定架体系,减少了埋管支架钢材用量,加快了埋管安装的施工进度。
In this paper,it is mainly introduced the technology and methods for installation construction of embedded pipe for backing deal of 1^# coke oven for the 3 million tons coking project of the new system of Baotou Steel. Moreover,it is elaborated the construction progress is quickened by improving the fixed mount and reducing the consumption of steel for embedded pipe.
出处
《包钢科技》
2013年第6期64-66,共3页
Science & Technology of Baotou Steel
关键词
埋管精度
底座安装
支架体系
precision of embedded pipe
installation of base
support system