摘要 据统计,压水堆核电站换料大修的集体剂量占年集体剂量的80%以上。大修期间高辐射作业项目多,人员集中,辐射风险高。大修集体剂量控制反映了核电站辐射防护管理水平的高低。秦山核电站已经顺利完成了十几次换料大修,通过不断的改进,辐射防护取得了一定的经验,机组大修的集体剂量控制有效。本文主要介绍秦山核电站大修期间辐射控制的实践与优化。 At the PWR nuclear power plants, more than 80% of Annual Collective Radiation Expo- sure Dose of workers can be attributed to the maintenance activities during refueling outage, so the collec- tive dose control effect is reflection of the radiation protection management level in NPP. During the out- age there are higher radiation works and more workers, so the exposure risk is definitely higher. Therefore the dose control during outage is one of the most important tasks for the radiation protection in NPP. Qin- shah NPP has completed 11 refueling outages, through gradual improvement, some good experience has been obtained and the collective dose has been controlled effectively. This paper introduces the dose con- trol practice and optimization at Qinshan NPP.
作者 徐宏明 张勇
出处 《核电工程与技术》 2013年第4期20-25,共6页 Nuclear Power Engineering and Technology
关键词 核电站 换料大修 辐射控制 nuclear power plant, refueling outage, dose control
  • 相关文献

参考文献4

  • 1夏益华,陈德淦,吴德强.辐射防护最优化原则及其应用.北京:原子能出版社.2000.
  • 2大亚湾核电站生产管理丛书.大修管理.北京.原子能出版社.2003.
  • 3张勇.核电站氧化运行及效果分析[J].辐射防护,2003,23(1):55-59. 被引量:17
  • 4徐宏明,姜建其.秦山核电站第八次大修辐射防护管理.核动力运行研究,2007.20(2):73.

二级参考文献1

  • 1[1]Cold shutdown with primary circuit oxygenation. Training file of EDF*SPT

共引文献17

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部