沙特扎瓦尔港口工程无围堰吹填施工工艺 被引量:8

Non-cofferdam reclamation method in Ras Al Khair Port,Saudi Arabia
下载PDF
导出
摘要 详细介绍了在沙特扎瓦尔港口工程吹填施工中,进行无围堰水上吹填,并利用防污帷幕遮挡悬浮细颗粒物以满足环保要求,在围堰施工完成后,再进行补吹形成陆域的施工工艺。该工艺经过一年多的工程实践取得成功,大大延长了可吹填施工时间,并获得了显著的经济效益。 This paper describes the details of non-cofferdam reclamation method taken in Ras Al Khair Sea Port Project, Saudi Arabia. A silt curtain was set up around reclamation area to control suspended solid for environmental protection. Complementary reclamation was carried out after the cofferdam was built to complete the whole reclamation area. This new method got great success after more than a year of engineering practice, increased construction period for reclamation works, and obtained remarkable economic benefits.
出处 《中国港湾建设》 2014年第2期62-65,共4页 China Harbour Engineering
关键词 无围堰 吹填 防污帷幕 环保 non-cofferdam reclamation silt curtain environmental protection
  • 相关文献

参考文献2

共引文献7

同被引文献33

引证文献8

二级引证文献11

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部