摘要
详细介绍了在沙特扎瓦尔港口工程吹填施工中,进行无围堰水上吹填,并利用防污帷幕遮挡悬浮细颗粒物以满足环保要求,在围堰施工完成后,再进行补吹形成陆域的施工工艺。该工艺经过一年多的工程实践取得成功,大大延长了可吹填施工时间,并获得了显著的经济效益。
This paper describes the details of non-cofferdam reclamation method taken in Ras Al Khair Sea Port Project, Saudi Arabia. A silt curtain was set up around reclamation area to control suspended solid for environmental protection. Complementary reclamation was carried out after the cofferdam was built to complete the whole reclamation area. This new method got great success after more than a year of engineering practice, increased construction period for reclamation works, and obtained remarkable economic benefits.
出处
《中国港湾建设》
2014年第2期62-65,共4页
China Harbour Engineering
关键词
无围堰
吹填
防污帷幕
环保
non-cofferdam
reclamation
silt curtain
environmental protection