摘要
介绍了道耶坎水电站枢纽工程的总体布置,着重对电站引水发电系统、水电站厂房、尾水、厂内外交通及厂区排水等进行了详细地论述,特别对水电站厂房的复杂地质条件,根据不同的情况,进行了不同的基础处理。
The overall layout of Thaukyegat II hydropower project is introduced. The water diversion for power genera- tion system, the power station, the tail water channel, the transportation system outside and inside the station, and the drainage system in the station are discussed in details. Due to the complicated geological conditions, the station founda- tion is treated based on different circumstances.
出处
《水电与新能源》
2014年第2期29-31,62,共4页
Hydropower and New Energy
关键词
道耶坎水电站
引水发电系统
电站厂房
Thaukyegat Ⅱ hydropower project
water diversion and power generation system
power station