结合具体工程 ,阐述了采用无支架组合钢模板翻升与塔式吊机垂直运输相结合的薄壁空心高墩的施工技术 ,包括结构形式、施工工艺及施工过程控制。
Connecting with concrete engineering,this paper expounds the construction techuique of thin-wall,hollow-core and high bridge piers by adopting the method of combining the lift of non-scaffolding composite steel forms with the vertical transportation of tower cranes,including structural forms,construction techniques and construction process control.
出处
《科技情报开发与经济》
2000年第2期68-69,共2页
Sci-Tech Information Development & Economy
关键词
薄壁空心高墩
无支架施工
施工技术
桥梁施工
thin-wall,hollow-core and high pier constrution without scaffolding construction technique