摘要
苗尾水电站土工膜心墙堆石围堰渗压计安装在工期特别紧、钻孔难度大、电缆保护受干扰的情况下,针对特定的影响因素应用PMP中的项目质量管理与项目时间管理的相关内容制定了相应的对策并付诸实施社,保证了渗压计的成功安装。有助于对围堰挡水期的渗漏情况进行分析,以采取相应的应急措施。
The installation of the geomembrane clay core rockfill cofferdam osmometer for construction of the Miaowei hydropower project has successfully been implemented after formulating corresponding meas-ures by applying PM P’s project quality control and project construction schedule management according to the specific factors under the situation of the tight construction schedule ,the great difficulty in boring and power cable being interfered .It helped make analysis of seepage of the cofferdam so as to take necessary e-mergency measures during the water retaining period .
出处
《云南水力发电》
2014年第1期7-10,共4页
Yunnan Water Power
关键词
土工膜心墙
堆石围堰
渗压计安装
直线工期
地质条件
geomembrane core wall
rockfill cofferdam
installation of osmometer
CPM
geological condi-tions