兰州深安黄河大桥V型主墩施工水化热分析

Analysis of Hydration Heat in Construction of V-type Pier for Shenan Yellow River Bridge in Lanzhou
下载PDF
导出
摘要 兰州深安黄河大桥主墩采用V型墩。V型墩构造复杂且局部混凝土几何尺寸较大,应进行水化热分析以避免施工过程中出现温度裂缝。水化热分析采用大型通用有限元程序ANSYS进行,先对V型墩结构进行热分析,然后将热分析得到的温度场作为体荷载施加到结构单元的节点上进行热—结构耦合场分析,最终得到结构的应力分布。水化热分析结果可指导V型墩施工方案的实施,并可为类似的工程提供有价值的参考。 The V-type pier is used for the main pier of Shenan Yellow River Bridge in Lanzhou.The structure of V-type pier is complicated and the local concrete geometry is larger.It is necessary to carry out the analysis of hydration heat to avoid the temperature cracks in the process of construction.The analysis of hydration heat is carried out by the large general finite element program ANSYS.Firstly the V-type pier structure is carried out of the heat analysis,then the temperature field obtained from the heat analysis as body load applied to the joint structure unit is analyzed of heat- structure coupled field,and finally the stress distribution of structure is obtained.The analysis result of hydration heat can guide the implementation of the V-type pier construction scheme,and can be referred for the construction of the similar projects.
出处 《城市道桥与防洪》 2014年第1期92-95,10,共4页 Urban Roads Bridges & Flood Control
关键词 大跨度拱桥 V型主墩 施工过程 有限元方法 水化热分析 long-span arch bridge main V-type pier construction process finite element method analysis of hydration heat
  • 相关文献

参考文献5

  • 1上海市政工程设计研究总院.兰州市深安黄河大桥工程主桥施工图设计文件[Z].2011.
  • 2GB50010--2010混凝土结构设计规范[S].北京:中国建筑工业出版社,2010.
  • 3JTG D62-2004.公路钢筋混凝土及预应力混凝土桥涵设计规范[S].2004.
  • 4宏润建设集团股份有限公司.兰州市深安黄河大桥工程主桥施工组织设计文件[Z].2012.
  • 5宏润建设集团股份有限公司.兰州市深安黄河大桥工程主桥V型墩施工仿真及水化热分析[z].2012.

共引文献59

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部