某电厂水库岸边取水工程施工实践 被引量:1

Construction Practice of Water Intake Engineering near the Reservoir
下载PDF
导出
摘要 为满足某电厂供水需求,需在某水库进行岸边取水工程(含取水竖井、引水隧道、引水明渠3部分)施工。通过短段掘砌逆作工艺,井筒壁溶洞导水并将导出的水作为水源的一部分,实现了井筒干封底,顺利完成井筒施工;采用顶管技术+管顶注浆技术在破碎岩体、涌水量较大地层成功完成引水隧道施工;通过岩塞爆破成功实现引水隧道和水库的连接;通过船载冲击成槽技术,实现了引水明渠的施工。 To meet the water supply demand of a power plant, the water intake engineering construction ( containing water intake shaft, draw water tunnel and open diversion channel) at a reservoir was needed.By means of the top-down method of excavation with lining alternated in short segments, guiding cavern water from shaft wall was derived as a part of the water source, and the shaft construction was completed with dry bottom-sealing.By pipe jacking and pipe top grouting technolo-gies, draw water tunnel was accomplished in the strata with broken rocks and abundant water inflow;by the rock plug blas-ting, the connection of the tunnel and the reservoir was successfully realized;and by percussive trenching technology, open diversion channel was constructed.
出处 《探矿工程(岩土钻掘工程)》 2014年第2期74-77,81,共5页 Exploration Engineering:Rock & Soil Drilling and Tunneling
关键词 取水工程 短段掘砌 逆作法 导水 干法封底 隧道顶管 冲击成槽 water intake engineering excavation with lining alternated in short segments top-down method guiding wa-ter dry bottom-sealing pipe jacking in tunnel percussive trenching
  • 相关文献

参考文献4

二级参考文献9

  • 1.水工建筑岩石基础开挖工程施工技术规范(SL 47-94)[M].北京:中国电力工业出版社,1995..
  • 2.土方与爆破工程施工及验收规范(GBT201-83)[M].北京:中国建筑工业出版社,1984..
  • 3.水工建筑物地下开挖工程施工技术规范(DL/T 5099-1999)[M].北京:中国电力工业出版社,2000..
  • 4沈芙河.爆破与锚喷实用工程技术手册[M].北京:中国计划出版社,1995.88-230.
  • 5安国梁等.现代矿井建设及地下工程施工技术[J].煤炭科学技术,1997,:21-22.
  • 6毛光宁.煤矿立井凿井技术装备的现状与展望.矿井建设技术论文集.徐州:中国矿业大学出版社.1996.21~31.
  • 7郭培里.加强探井机械化配套设备的研究.煤矿建设科研40年.北京:煤炭工业出版社,1997.205-208.
  • 8龙志阳.我国立井整体移动金属模板的现状与发展.煤矿建设科研40年.北京:煤炭工业出版社,1997.215-220.
  • 9李俊良,姜利.立井混合作业机械化配套施工[J].建井技术,1989(1):16-20. 被引量:6

共引文献14

同被引文献8

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部