期刊文献+

弱胶结未成砂岩挑顶斜井与隧道初支结构转换技术 被引量:6

The Conversion Technology of Weak Cementation Sueshige Sandstone Ripping Inclined Shaft and Tunnel Initial Branch Structure
下载PDF
导出
摘要 针对兰渝铁路桃树坪隧道2号斜井的弱胶结未成砂岩的地质条件,提出了一种利用挑顶斜井空间转换施工隧道初支结构的方法.通过提高斜井挑顶断面、井口钢门架、井端大拱脚、空架隧道初支、回填拱部空间等施工技术,能安全实施斜井与正洞初期支护结构受力体系的转换,保证施工安全. According to Lan-Yu railway tunnel Taoshuping second inclined shaft weak cementation sueshige sandstone geological characteristics,describes a use of space conversion inclined shaft to tunnel initial branch structure.Construction by increasing the construction technology of inclined shaft ripping ripping,wellhead steel gantry,the large arch foot of ibata,empty frame tunnel early supported,backfill arch part space,better finished inclined shaft with initial positive supporting stress structure system conversion,to ensure construction safety.
作者 刘新英
出处 《兰州交通大学学报》 CAS 2014年第1期39-43,共5页 Journal of Lanzhou Jiaotong University
关键词 铁路隧道 未成砂岩 斜井挑顶 受力结构 转换技术 railway tunnel sueshige sandstone inclined shaft ripping stress structure conver-sion technology
  • 相关文献

参考文献6

  • 1韩庚瑞.地下工程新奥法[M].北京:科学出版社,1987.
  • 2吴建兵.软岩隧道快速掘进中变形预测及支护方案优化的研究[D].武汉:武汉理工大学,2001.
  • 3李海威,李德武,常卫锋.浅埋偏压隧道围岩力学与变形研究[J].兰州交通大学学报,2012,31(1):43-46. 被引量:9
  • 4钟桂彤.铁路隧道[M].北京:中国铁道出版社,2000.
  • 5中华人民共和国铁道部.TB10204-2002铁路隧道施工规范[S].北京:中国铁道出版社,2002.
  • 6中华人民共和国铁道部.TB10417-2003/J287-2004铁路隧道工程施工质量验收标准.北京:中国铁道出版社,2004.

二级参考文献2

共引文献28

同被引文献39

引证文献6

二级引证文献20

相关作者