摘要
通过对云驾岭煤矿12802工作面拆除与12806工作面安装的分析,深入研究了工作面生产工艺中最关键的环节。支架回收工艺是否合理,顺序是否正确,巷道及工作面地质条件的优劣,直接决定着支架的回收与安装速度,制约正常生产,是综采工作面支架回收与安装中的特殊工艺。
Through the analysis of the 12802 working face demolition and installation of 12806 face in Yunjialing Mine, the most critical part of the working face production process was deeply studied. Support recycling process, sequence, geological conditions of roadway and working face good or not decided support recycling and installation of speed, which restricted the production, was a special process in fully mechanized working face support recycling and installation.
出处
《煤炭与化工》
CAS
2014年第2期97-98,155,共3页
Coal and Chemical Industry
关键词
综采大坡度工作面
铺双网支护
掩护式拆除
免拆装支架
fully mechanized large slope face
pave twin wire support
cover type
without dismantling scaffolds