摘要 盾构始发与到达施工是盾构法建造区间隧道的关键工序,也是施工频繁的常见工序。一旦发生事故,将造成较大人员伤亡和经济损失。将失效模式与效应分析(FMEA)法引入地铁盾构始发与到达施工风险评估。通过对该施工工序特点剖析,识别失效模式,制定风险评估标准;通过专家问卷调研,按FMEA法计算风险优先指数(RPN),并对各类风险进行灾害严重性定级;最后,通过对国内地铁施工典型事故案例分析,验证FMEA法评估风险的有效性。 The construction at TBM launching & break through area is a critical and frequent common process of tunneling construction. The accident will resuh in severe casualties and economic 1.osses. This paper presents construction risk identification and evaluation at TBM launching & break through area based on Failure Mode and Effect Analysis (FMEA). Firstly tunneling construction process features are analyzed, failure modes are identified, and risk evaluation criterions are formulated. Secondly Risk Priority Number (RPN) is calculated according to expert questionnaires, risk-disastrous severity is classified. Lastly the validity of risk evaluation is verified through case analysis of typical metro accidents at TBM launching & break through area.
作者 余宏亮
出处 《价值工程》 2014年第10期123-125,共3页 Value Engineering
基金 武汉科技大学高层次人才引进基金资助项目(060197)
关键词 地铁盾构 FMEA 风险评估 始发与到达 TBM FMEA risk evaluation launching & break through
  • 相关文献

参考文献16

二级参考文献107

共引文献512

同被引文献9

引证文献1

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部