钢管砼拱桥泵送顶升混凝土施工技术探讨 被引量:2

Construction Technology on Pumping Concrete into Steel Tube of Encased Arch Bridge
下载PDF
导出
摘要 钢管内混凝土与钢管共同形成钢管拱桥的主要受力结构,是钢管拱桥的"生命线"工程,因此钢管内混凝土能否顺利施作具有重大意义。结合实际施工对混凝土的泵送过程的几个技术问题进行论述:混凝土的技术性能、拱肋内混凝土的泵送先后次序安排、钢管所承载的泵送压力计算、泵送口的截止阀门设置、进料短管与钢管拱肋间的连接构造、针对缀板的加强措施、输送泵的选型、减小泵送压力的施工措施等,以期对钢管内砼施工提供技术借鉴。 Concrete in steel tube together with steel tube forms the main stress bearing structures, which is the life of steel- tube arch bridge. Therefore, it is very important to ensure concrete to be conducted to steel tube. Based on practice of pumping concrete into steel tube, the author analyzes several technical problems that may occur during concrete pumping such as the concrete technical performance, pumping sequence arrangement for rib concrete, calculation of the pressure beard by steel pipe, stop valve arrangement at pumping entrance, connection structure between short feeding tube and rib of steel tube, strengthening measures for batten plate, type selection for conveying pump and construction measures to reduce pumping pressure, etc. so as to provide reference for concrete construction in steel tube.
作者 李圣荣
出处 《铁道建筑技术》 2014年第1期75-78,共4页 Railway Construction Technology
关键词 钢管砼 泵送顶升 混凝土灌筑 拱桥 steel tube concrete pumping and lifting pouring concrete arch bridge
  • 相关文献

参考文献1

  • 1中交第一公路工程局有限公司.JTG/TF50-2011公路桥涵施工技术规范[S].北京:人民交通出版社,2011:126-127.

同被引文献17

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部