摘要
武黄城际铁路鄂州特大桥,30~32号墩连续梁上跨武九电气化铁路,连续粱采用现浇支架法施工。以鄂州特大桥支架体系的拆除为例,详细介绍了在上跨电气化铁路的条件下,现浇连续梁支架体系的拆除施工技术及施工注意事项。
The continuous beam between 30 to 32# pier of Ezhou Extra-large Bridge on Wuhan to Huangshi Intercity Rail-way cross over Wuhan to Jiujiang electrified railway. Continuous beam is built with cast-in-place construction scaffolding. This article, taking the removal of the support system of the Ezhou Extra-large Bridge as an example, introduces the removal of cast-in-place continuous beam support system and construction points in detail for attention over electrified railway.
出处
《铁道建筑技术》
2014年第2期23-26,共4页
Railway Construction Technology
关键词
上跨电气化铁路
支架拆除
整体平移
连续梁
overcross electrified railway
tents demolition
the overall level translation
continuous beam