摘要
利用二维动态模型对澳门附近水域治导线工程前后对水体纳污能力的影响进行分析 ,结果证明工程实施后主干流水环境容量略有增大 ,工程是有利的 .此外 ,还提出了单元体水环境容量的概念 ,对澳门附近水域治导线工程前后水环境容量空间分布作了初步探讨 .
A two dimensional dynamic model is used in the analysis of the impact of a planned regulating project on the dissolving capacity of the water body near Macao. The results from computation show that the dissolving capacity of the water body of the Pearl River would be slightly increased after the project is constructed. In the paper, a concept of unit water dissolving capacity is proposed and used in the analysis of the spatial variation of the dissolving capacity in the area near Macao before and after the planned regulating project.
出处
《河海大学学报(自然科学版)》
CAS
CSCD
北大核心
2001年第1期93-95,共3页
Journal of Hohai University(Natural Sciences)
关键词
水环境
容量
动态模型
河口治理
珠江河口
dissolving capacity
dynamic model
dissolving capacity of unit water