摘要
用线性规划法,在PV图控制下优化生产剥采比,用人机交互式模拟技术编制采剥生产进度计划.开发出一套易为矿山人员接受的可在微机上运行的软件,具体编制了某矿进度计划.
Using linear programming and computer similar tcchnigue,a set of software is developed to optimum mine production scheduling and applied to a open pit mine. This software can be run in microcomputer and easy to be accepted by mine technical personnel.
出处
《广西大学学报(自然科学版)》
CAS
CSCD
1991年第2期78-82,共5页
Journal of Guangxi University(Natural Science Edition)
关键词
露天矿
采剥
线性规划
计算机模拟
open-pit mines
lincar programming/ production scheduling optimization
computer similar