摘要
通过干-湿两级脱硫除尘设施在20蒸吨及以下锅炉上的应用,从除尘、脱硫主体设施设计、循环水系统、操作过程、管理方面分析了影响脱硫除尘效果的因素,在工艺整体设计、设备选型和循环水系统建设上提出了建议,在设施操作和管理上提出了具体看法和观点,为今后选用此工艺提供借鉴和帮助。
By applied dry-wet two stage desulphurization and dust removal facilities in 20 steam tons and below boilers, ana-lyzed the factors effect desulfurization and dust removal from dedusting, desulphurization main facilities design, circulating water system, operation process and management, suggestions are proposed in overall design, equipment selection and circulating water system construction, the specific opinions and viewpoints are put forwarded in facility operation and management, these provide reference and help for select this craft in the future.
出处
《神华科技》
2014年第2期93-96,共4页
Shenhua Science and Technology
关键词
干
-
湿两级
脱硫除尘
效率
Dry-Wet-Two-Stage
Desulphurization and Dust Removal
Efficiency