摘要
糯扎渡水电站右岸泄洪洞弧形工作闸门为一高水头潜孔式闸门,外形尺寸大,安装作业空间狭窄,安装非常困难。本文介绍了该闸门的整个安装程序,旨在供今后类似闸门的安装参考。
The radial working-gate of flood discharge tunnel on the right bank of Nuozhadu Hydropower Station is a high head submerged orifice-gate with a large outline dimension and a narrow space for installation, and then the installation of it is quite difficult. The whole process of the installation of the gate is introduced herein, so as to provide a reference for the installation of the similar gates concerned.
出处
《水利水电技术》
CSCD
北大核心
2014年第3期24-26,29,共4页
Water Resources and Hydropower Engineering
关键词
糯扎渡水电站
弧形工作闸门
安装工艺
Nuozhadu Hydropower Station
radial working-gate
installation technology