集中供热直埋单式轴向型膨胀节安装施工要点

Construction essentials of directly buried single axial expansion joints for central heating project
下载PDF
导出
摘要 结合甘肃省张掖市集中供热工程直埋单式轴向型膨胀节施工实践体会,从安装前的检查、安装中的重点要求、系统试压与清洗、管路保温、回填等方面介绍了其安装施工要点。4个供暖期的正常供热运行证明该种施工技术具有合理性和可行性。 Based on the construction experience of directly buried single axial expansion joints in central heating project at Zhangye city in Gansu province, presents the construction essentials including the examination before installation, crucial requirements during installation, pressure test and cleanout, pipe insulation, and backfill. The normal running of four heating periods proves that the construction technique is reasonable and feasible.
作者 成义祥
出处 《暖通空调》 北大核心 2014年第4期96-99,共4页 Heating Ventilating & Air Conditioning
关键词 集中供热 直埋单式轴向型膨胀节 安装施工 技术要点 试压 清洗 保温 central heating, directly buried single axial expansion joint, installation and construction, technical essential, pressure test, cleaning, thermal insulation
  • 相关文献

参考文献7

  • 1甘肃省暖通空调学术委员会.DBJ25-66-96甘肃省热水热网直埋敷设技术规程[s].兰州:甘肃科学技术出版社,1996.
  • 2徐志滨,王向东,钱江.城市集中供热有补偿直埋热水管道几种布置型式[J].管道技术与设备,2007(1):45-46. 被引量:1
  • 3邱广涛,杨知我,丰艳春,汪锡铎,赵金星.波纹膨胀节失效因素与预防[J].管道技术与设备,2001(5):14-16. 被引量:8
  • 4中国船舶重工集团公司第七二五研究所,南京晨光航天应用技术股份有限公司,中国石化工程建设公司,等.GB/T12777--2008金属波纹管膨胀节通用技术条件[s].北京:中国标准出版社,2008.
  • 5建设部城市建设研究院.CJ/T3016-93城市供热管道用波纹管补偿器Es].北京:中国建筑工业出版社,1993.
  • 6北京市热力集团有限责任公司.CJJ28-2004城镇供热管网工程施工及验收规范Is].北京:中国建筑工业出版社,2004.
  • 7大庆石油管理局油田建设设计研究院,胜利石油管理局油建一公司.SY/T0415-96埋地钢质管道硬质聚氨酯泡沫塑料保温层技术标准[s].北京:石油工业出版社,1996.

二级参考文献3

共引文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部