摘要
现行《水利工程水利计算规范》(SL 104-95)中缺少灌溉水库径流调节的具体方法,水库工程设计中通常使用的调节计算办法存在一些不合理性。针对这一问题,通过修正常规计算方法中不合理的计算条件,简化计算过程,选择对常规的长系列时历法(列表法)的计算方法和程序进行了改进,采用长系列连续调节计算,可以适用于多种调节性能的灌溉水库。改进后的方法经过多项工程使用检验,计算过程合理,调节结果准确,水库灌溉供水量和灌溉保证率比常规方法有所增加。
Regulation for Water Conservancy Computation of Water Projects SL 104-95 lacks the specific methods on runoff reg-ulation of irrigation reservoir ,and the calculation method commonly used in reservoir engineering design is not reasonable to some extent .In this paper ,an improved calculation method was proposed .The improved method modified the calculation meth-od of long time series in the conventional method and applied the long series continuous calculation .It can correct the unreasona-ble calculation conditions in the conventional method and simplify the calculation process ,and it can be applied for the irrigation reservoir with a variety of regulation performances .The improved method was verified by multiple engineering projects ,and the results indicated the calculation process is reasonable and regulation results are accurate .Moreover ,irrigation water and irriga-tion assurance increased using the improved method compare with those obtained from the conventional method ,.
出处
《南水北调与水利科技》
CSCD
北大核心
2014年第2期125-128,共4页
South-to-North Water Transfers and Water Science & Technology
关键词
灌溉水库
时历法
径流调节
灌溉供水量
灌溉保证率
irrigation reservoir
time series method
rrunoff regulation
iirrigation water supply
iirrigation assurance