期刊文献+

考虑载荷流泄时盾构机T形焊接结构疲劳可靠性分析 被引量:2

FATIGUE RELIABILITY STUDY ON T-WELDED COMPONENT OF SHIELD MACHINE CONSIDERING LOAD SHEDDING
原文传递
导出
摘要 T形焊接结构是盾构机刀盘的关键结构之一,焊接处裂纹在亚临界的扩展是其疲劳失效的关键因素.文章在考虑载荷流泄情况下,基于概率断裂力学的一次二阶矩方法提出了一种新的结构疲劳可靠性分析方法.将该方法应用到某盾构机T形焊接结构,给出了考虑与不考虑载荷流泄两种情况下结构疲劳可靠性计算结果,并用Monte Carlo方法验证了文章方法的有效性;利用最小二乘法拟合出了载荷流泄系数对该T形焊接结构疲劳可靠性的影响曲线,将该曲线划分了三个区域:高、中、低疲劳失效区,实际工程在盾构机T形焊接结构疲劳可靠性设计时,将T形焊接结构的厚度作为一个设计变量,而低失效区可以作为一个可靠度约束条件.结果表明在考虑和不考虑载荷流泄时,T形焊接结构的疲劳失效概率分别是8.2644×10-5和3.4314×10-4,即载荷流泄提高了结构的疲劳可靠度;研究成果对实际工程上盾构机刀盘的维修、检验计划和设计都有一定的理论指导意义. T welded component is one of the key structures of the shield machine cutter-head,and sub- critical crack in the weld extensions is a key factor in its fatigue failure. By using probabilistic fracture me chanics based on the first order second moment method,a new structural fatigue reliability analysis method considering load shedding was applied to a T-welded shield structure in this contribution. The results of structural fatigue reliability were obtained in the cases of with and without considering load shedding. The accuracy of this method was verified using Monte Carlo method. Then a curve that describes the load shed- ding impacts on the T-welded structure fatigue reliability was fitted via least square method. Based on the fitted curve, three zones including high, medium and low were divided. The thickness of T-welded structure was adopted as a design variable in the practical project design of fatigue reliability,in which low fatigue failure zone may be used as a reliahility constraint. The results showed that the fatigue failure probabilities were 8.2644×10^-5 and 3.4314×10^-4,respectively,which indicated that load shedding could improve the structure fatigue reliability. These results can offer a theoretical guidance for the maintenance,inspection plan and design of shield machine cutter-head.
出处 《固体力学学报》 CAS CSCD 北大核心 2014年第2期182-188,共7页 Chinese Journal of Solid Mechanics
基金 国家科技支撑计划项目(2012BAH09B02) 高等学校博士学科点专项科研基金(20120161130001) 湖南大学汽车车身先进设计制造国家重点实验自主课题基金(71275003)资助
关键词 T形焊接结构 载荷流泄 疲劳可靠性 盾构机 一次二阶矩 MONTE CARLO方法 T-welded structure, load shedding, fatigue reliability, shield machine, first order secondmoment method, Monte Carlo method
  • 相关文献

参考文献15

  • 1胡国良,龚国芳,杨华勇,邢彤.盾构掘进机模拟试验台液压系统集成及试验分析[J].农业机械学报,2005,36(12):102-105. 被引量:14
  • 2赵宝虎,王燕群,岳澄,亢一澜,王辉.盾构始发过程反力架应力监测与安全评价[J].工程力学,2009,26(9):105-111. 被引量:20
  • 3Deng K S, Tang X Q,Wang L P,et al. Research on characteristics of deformation in thrust system for EPB shield machines[J]. Tunneling and Underground Space Technology, 2011,26 : 15-21.
  • 4Deng K S,Tang X Q, Wang L P,et al. Force trans mission characteristics for the non equidistant ar rangement thrust systems of shield tunneling ma ehines[J]. Tunneling and Underground Space Tech nology, 2011,20 : 588-595.
  • 5Dong P. A structural stress definition and numerical implementation for fatigue analysis of welded joints [J]. International Journal of Fatigue, 2001, 23: 865-876.
  • 6Lindgren C, Sperle J O, Jonsson M. Fatigue strength of spot welded beams in high strength steels [J]. Welding in the World,1996,37(1) :90-104.
  • 7Hyungyil L, Nahmho K, Tae S L. Overload failure curve and fatigue behavior of spot-welded specimens [J]. Engineering Fracture Mechanics, 2005, 72: 1203-1221.
  • 8Fersini D,Pirondi A. Analysis and modeling of fatigue failure of friction stir welded aluminum alloy single- lap joints[J]. Engineering Fracture Mechanics, 2008, 75:790-803.
  • 9Yan H Z, Stephen J Maddox. Fatigue life prediction for toe ground welded jointsEJ2. International Journal of Fatigue,2009,31 : 1124-1136.
  • 10Sonsino C M. Multi-axial fatigue assessment of welded joints-recommendations for design codes[J]. In- ternational Journal of Fatigue, 2009,31 : 173-187.

二级参考文献46

共引文献42

同被引文献23

  • 1丁峻宏,金先龙,郭毅之,汤华,杨洪杰.土壤切削大变形的三维数值仿真[J].农业机械学报,2007,38(4):118-121. 被引量:37
  • 2丁峻宏,金先龙,李根国,吴建成,杨洪杰.基于并行计算的盾构机刀盘三维切削仿真[J].系统仿真学报,2007,19(23):5376-5379. 被引量:5
  • 3DENG Kong-shu, TANG Xiao-qiang, WANG Li-ping, et al. Force transmission characteristics for the non-e- quidistant arrangement thrust systems of shiled tunne- ling machines[J']. Tunneling and Underground Space Technology, 2011, 20(5): 588-595.
  • 4DENG Kong-shu, TANG Xiao-qiang, WANG Li-ping, et al. Force transmission characteristics for the non-e- quidistant arrangement thrust systems of shiled tunne- ling machines I-J. Tunneling and Underground Space Technology, 2011, 20(5): 588-595.
  • 5SUSILA E, HRYCIW R D. Large displacement FEM modeling of the cone penetration test (CPT) in normally consolidated sand[J]. International Journal for Numeri- cal and Analytical Methods in Geomechanics, 2003(27) : 585-602.
  • 6YUAN DI, TADANOBU SA. Computational model- ing of large deformation of saturated soils using an ALE finite element method[J]. Annuals of Disas Prev Res Inst, Kyoto Univ, 2004, 47(C): 171-182.
  • 7GOEL GAURAV S. A numerical study of tillage tool wear during plowing of sandy soilI-DJ. Charlotte: Uni- versity of North Carolina, College of Mechanical Engi- neering, 2013: 67-70.
  • 8廖公云,黄晓明.ABAQUS有限元在道路工程中的应用[M].南京:东南大学出版社,2008:82-83.
  • 9谭青,屠昌锋,暨智勇,夏毅敏.盘形滚刀切割岩石的数值仿真[J].现代制造工程,2009(2):62-64. 被引量:17
  • 10刘国斌,龚国芳,朱北斗,施虎.基于BP神经网络的盾构推进速度自适应PID控制[J].工程设计学报,2010,17(6):454-458. 被引量:14