期刊文献+

高面板堆石坝变形性态分析与研究 被引量:4

Analysis and Research on Deformation State of High Concrete Face Rockfill Dam
下载PDF
导出
摘要 结合梨园水电站面板堆石坝,根据大坝填筑到坝顶时不同变形监测方法所得的监测成果,对大坝进行三维有限元正反分析,深入评价高面板堆石坝施工质量及运行状况,并总结高面板堆石坝沉降范围,提出大坝堆石体平均压缩模量与沉降比(沉降量占坝高的百分比)的关系,据此评价梨园水电站面板堆石坝施工质量。 Combined with the concrete face rockfill dam (CFRD) of Liyuan Hydropower Station, the deformation data during dam filling period which obtained by different deformation monitoring methods are evaluated by inversion analysis, and then the dam is analyzed by three-dimension finite element. The evaluation results of deformation monitoring data are used to assess the construction quality and operation condition of high CFRD. The settlement range of high CFRDs is also summarized herein and then the relationship between the average compression modulus of rickfill body and the settlement ratio (the percentage of settlement with dam height) is proposed, which is taken as the basis to evaluate the construction quality of CFRD of Liyuan Hydropower Station.
出处 《水力发电》 北大核心 2014年第5期30-32,57,共4页 Water Power
关键词 高面板堆石坝 变形监测 三维有限元分析 梨园水电站 high concrete face rockfill dam deformation monitoring three-dimensional finite element analysis Liyuan Hydropower Station
  • 相关文献

参考文献4

  • 1贾金生,袁玉兰,马忠丽.中国与世界大坝建设情况[C].水电2006国际研讨会论文集.昆明:中国水电顾问集团昆明勘测设计研究院,2006.1205-1209.
  • 2殷宗泽,等.土工原理[M].北京:中国水利水电出版社,2000.
  • 3魏亮亮,刘绍川,杨传俊,等.梨园水电站面板堆石坝填筑坝料试验报告[R].长沙:中国水电顾问集团中南勘测设计研究院,2013.
  • 4邓军,聂成良,罗旭东,等.梨园水电站枢纽区安全监测工程2012年度监测报告[R].昆明:梨园水电站枢纽区安全监测工程“昆·长”联合体项目部,2012.