基于Pareto进化算法的建筑工程多目标优化研究 被引量:1

Research on construction multi-objective optimization based on Pareto-evolutionary algorithm
下载PDF
导出
摘要 工期短、成本低、资源均衡是建设单位追求的目标,通常各目标之间相互冲突,本文提出Pareto进化算法理论求解此类多目标优化问题,编制进化算法优化模型,采用Pareto理论和精英保留策略进行目标值选择,并引入小生境理论保持种群的多样性,产生多种施工方案供管理者选择。通过工程实例,验证了该模型正确可行。 In order to solve the conflicts between duration compression,a low cost and resource equalization in construction industry, the theory of Pareto-evolutionary algorithm is intro- duced, the evolutionary algorithm optimization model is established. Meanwhile , the Pareto the- ory and elitism strategy are used for multiple target selection, the Niche theory is used to main- tain the diversity of population, finally several construction methods are produced for manager to select. The result of the engineering example shows the algorithm has higher fitting preci- sion.
出处 《河北农业大学学报》 CAS CSCD 北大核心 2014年第2期133-137,共5页 Journal of Hebei Agricultural University
关键词 Pareto进化算法 多目标优化 精英保留策略 建筑工程 小生境理论 Pareto-evolutionary algorithm multi-objective optimization elitism strategy archi-tectural engineering niche theory
  • 相关文献

参考文献8

二级参考文献34

  • 1杨耀红,汪应洛,王能民.工程项目工期成本质量模糊均衡优化研究[J].系统工程理论与实践,2006,26(7):112-117. 被引量:55
  • 2谢尊渊.建筑施/[M].北京:中国建工出版社,1998.
  • 3建筑施工手册编写组.建筑施工手册[S].北京:中国建工出版社,2000.
  • 4马振华.运筹学与最优化理论卷[M].北京:清华大学出版社,1998.
  • 5[2]Abido M.A Niched Pareto Genetic Algorithm for Multiobjective Environmental/Economic Dispatch[J].Electrical Power&energy Systems,2003,(25):97-105.
  • 6[3]Mark E,Alex M,Jeffrey H.Multi-objective Optimal Design of Groundwater Remediation Systems:Application of the Niched Pareto Genetic Algorithm[J].Advance in Water Resources,2002,25:51-65.
  • 7CHEN PcrHan,WENG Hai-jie.A two-phase GA model for resource-constrained project scheduling[J].Automation in Construction:2009,18:485-498.
  • 8ZHENG Daisy X M,THOMAS S Ng,KUMARAswAMY Mohan M.Applying a Genetic Algorithm-Based MultiobjectiveApproach for Time-Cost Optimization[J].Journal of Construction Engineering and Management,2004,4:168-176.
  • 9Khaled El-Rayes.Time-Cost-Quality trade-off analysis for highway construction[J].Journal of Construetion Engineering and Management:2005,131(4):477-486.
  • 10Kuhn H W, Tucker A W. Nonlinear programming[ C]. In j Neyman editor Proceedings of the Second Berkeley Symposium on Mathematical Statistics and Probability, Berkeley, Califomia: University of Califomia Press, 1951:481 - 192.

共引文献90

同被引文献7

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部