文章结合南宁大桥主桥承台大体积混凝土施工实例,分析了大体积混凝土产生裂缝的原因,并从承台大体积混凝土施工方案、材料选择、配合比设计、现场浇筑质量控制等方面,介绍了保证承台大体积混凝土施工质量的控制措施以及取得的效果,对类似工程有一定的借鉴作用。
In combination with the mass concrete construction example of main bridge pile cap in Nan- ning Bridge,this article analyzed the causes for the cracks of mass concrete,and from the mass con- crete construction program of pile cap, material selection, mix ratio design, cast-in-situs quality control and other aspects,it introduced the control measures to ensure the mass concrete construction quality of pile caps as well as the results achieved,with a certain reference significance for similar projects.
出处
《西部交通科技》
2014年第3期57-59,70,共4页
Western China Communications Science & Technology
关键词
南宁大桥
主桥
承台大体积混凝土
施工
质量控制
Naming Bridge
Main bridge
Mass concrete of pile cap
Constrtction