期刊文献+

桥头跳车作用机理与处理措施研究

Study on Action Mechanism and Treatment Measures of Bridgehead Bump
下载PDF
导出
摘要 桥头跳车妨碍道路舒适性的难题之一,从力学上分析了桥头跳车作用机理,提出桥头沉降差的控制值。研究表明台背填土沉降、桥台基础的沉降、水温、设计计算理论是导致桥头跳车的主要因素,针对性提出增加地基整体刚度及承载力、设置刚柔均匀过渡、处理好排水、改进设计计算方法等处理措施。 The bridgehead bump is one of difficulties to affect the road comfort.The article mechanically analyzes the action mechanism of bridgehead bump,and puts forward the control value of bridgehead settlement difference.The study shows that the backfill setdement,abutment foundation settlement,water temperature and design calculation theory are the main factors to cause the bridgehead bump.The article describes the treatment measures of increasing the integral rigidity and bearing capacity,setting up the rigid-flexibility homogeneous transition,treating the drainage well and improving the design calculation method.
作者 张帆 刘毅
出处 《城市道桥与防洪》 2014年第4期232-234,13,共3页 Urban Roads Bridges & Flood Control
关键词 桥头跳车 作用机理 处理措施 bridgehead bump action mechanism treatment measures
  • 相关文献

参考文献8

  • 1冯忠居,方贻立,龚坚城,朱建斌.高等级公路桥头跳车的危害及其机理的分析[J].西安公路交通大学学报,1999,19(4):33-35. 被引量:131
  • 2王秉纲,胡长顺.跨越构造物炉面结构设计与施工技术研究总报[R].1999.
  • 3Wahls,H. E.NCHRP Synthesis of Highway Practice 159:Design and Construction of Bridge Approaches[J].Transportation Research Board, National Research Council,Washington, D. C,1990,27.
  • 4Stark TD,SM Olson,JH Long, Differential Movement at the Embankment/ Structure Interface-Mitigation and Rehabilitation[R].Illinois:ReportNo. LAB-H 1 ,FY93 ,DOT,Springfield ,Illinois, 1995.
  • 5JTJ 034-2000,公路路面基层施工技术规范[S].2000.
  • 6JTGD30-2004公路路基设计规范[S].2004.
  • 7JTJ/T 019.98,公路土工合成材料应用技术规范[S].1999.
  • 8张贵婷,方芳.土工网在高速公路桥头跳车处理中的应用[J].中南公路工程,2000,25(4):48-49. 被引量:3