摘要
南水北调中线工程南阳三标膨胀土渠段,在经历数次降雨后,渠段局部土体在多次干湿循环后强度降低、地表水进入裂隙、改性土未及时回填到位,造成渠坡两次滑坡和抗滑桩倾覆破坏。经及时处理,快速施工,确保了中线主体按时完工。
The slope and piles of the third bided-section in Nanyang were broken, because strength of swelling clay rapidly discreased after precipitation, ground water was saturated into gap and cement mixed swelling clay was not filled in certain height. After dealing with it on time and quick construction, the completing time of the South-to-North Water Transferred Project middle route will be flexed.
出处
《水科学与工程技术》
2014年第2期94-96,共3页
Water Sciences and Engineering Technology
关键词
滑坡
干湿循环
强度降低
抗滑桩
破坏
快速施工
slope sliding
dry-wet cycling
strength discrimination
pile
destroy
quick construction