摘要
为了控制江仓一号井项目的建设投资,依照矿井建设的内在逻辑,结合当地高原高寒的客观环境,采取以投资为中心,从设计阶段控制项目造价、施工阶段控制各项费用的发生,探索出了以项目设计为重点,以工程建设为主线,以投资控制为中心的资金控制基本框架,完成了项目建设的投资目标。
In order to control construction investment of Jiangcang No. 1 project, according to the inherent logic of mine construction, combined with local plateau alpine objective environment, investment as the center was taken, control project cost from the design stage, construction stage control expenses, focusing on project design was explored, project construction as the main line, centered on investment control of the basic framework of capital controls, project construction investment goal was achieved.
出处
《煤炭与化工》
CAS
2014年第3期119-120,共2页
Coal and Chemical Industry
关键词
矿井建设项目
工程造价
投资控制
综合效益
mine construction project
project cost
investment control
comprehensive benefits