摘要
线性监测是桥梁施工控制的重要环节,是确保桥梁的安全施工过程的关键环节。结合长白山国际旅游胜地2号桥的主拱施工监控程序,介绍了监控内容和关键技术。考虑在建设过程中的各种因素,通过线性调整处理,确保压力和主拱线形满足设计要求。
Linear monitoring is an important link of bridge construction control, which is conducted in key processes of construction to ensure the security of bridge in construction procedure. Combining with main arch construction monitoring program of No. 2 bridge in north district of Changbai international tourism resort, main content and key technologies are recommended. Considering the various influential factors during the construction process, linear adjustment is handled to ensure that the stress and linear of main arch meet design requirements.
出处
《北方交通》
2014年第4期43-45,共3页
Northern Communications
关键词
线性监控
预压力
贝雷梁
Linear monitoring
Pre - loading pressure
Bailey beam