摘要
本文介绍了富余煤气60MW发电机组投运前后水钢炼铁供电系统的运行情况,分析了发电机组投运后对炼铁供电系统运行的负面影响。通过调整供电系统,收到满意的供电效果。
This article introduced operation of electric power supply system for ironmaking before and after 60 MW coal-gas electric set was put into use in Shuigang and analyzed adverse effect of the electric set on the electric power supply system. Through adjusting the system, we obtained desirable effect of electric power supply.
出处
《水钢科技》
2014年第1期41-44,共4页
Shuigang Science & Technology
关键词
炼铁
煤气
发电
供电
ironmaking
coal gas
electric power generation
electric power supply