摘要
基于单线计轴自动闭塞在成昆、成渝、内宜等管段内,作为提高运输能力的设备,大部分在既有设备上增加,施工调试存在许多难点。结合成昆、成渝单线计轴自动闭塞工程的实施,针对新的技术条件,总结技术改进方案,同时对新旧设备结合调试,提供可行的试验方法。
Chengkun railway, Chengyu railway and Neiyi railway have districts of automatic block with single axle counters, and the axle counters are used as equipment to improve transport capacity. Because they need to be added mostly on existing equipment, construction commissioning have many difficulties. Combined with the project implementation of automatic block with single axle counters for Chengkun and Chengyu railways, the paper provides some feasible test methods according to the new technical conditions based on summarizing the technical improvement scheme and conducting commissioning of old and new equipment.
出处
《铁路通信信号工程技术》
2014年第2期58-61,共4页
Railway Signalling & Communication Engineering
关键词
单线计轴自动闭塞
既有线
结合电路
调试
automatic block with single axle counter
existing railway
combined circuit
commissioning