西宁火车站改造工程桩基抗拔极限承载力的试验及模型研究

Experimental and Modeling Study on Pullout Ultimate Bearing Capacity of Pile Foundation in XiNing Railway Station Reconstruction Project
下载PDF
导出
摘要 地下工程中承载力的确定对地下工程的施工与设计有着重要意义,但受荷载装置、试桩费用、工程进度等条件限制,许多桩未能加载至破坏状态,不能直接得到极限承载力等重要参数.以西宁火车站改造工程的抗拔试验为例,根据静载试验得到的Q-S曲线,运用MATLAB软件采用最小二乘法分别拟合出3种抗拔极限承载力预测函数模型的参数,并提出三项式模型适用于该地区的抗拔桩极限承载力预测模型. Determining the bearing capacity of underground engineering has an important significance for the de- sign and construction, But due to the limit of loading device, test cost, engineering schedule and other condi- tions, many piles can' t be loaded, which can not directly get the important parameters like ultimate bearing ca- pacity and so on. Pull-out test in Xining Railway Station renovation project is taken as the example, based on Q- S curves obtained from the static loading tests, and by using MATLAB software, parameters of three kinds of pre- diction function models of pullout ultimate bearing capacity are fitted through least square method, and trinomial model a prediction model of the ultimate bearing capacity of uplift pile which is suitable for this area is pro- posed.
作者 徐树锋 王旭
出处 《兰州工业学院学报》 2014年第2期58-61,共4页 Journal of Lanzhou Institute of Technology
关键词 抗拔试验 极限承载力 预测模型 Pull-out test ultimate bearing capacity prediction model
  • 相关文献

参考文献4

二级参考文献12

共引文献340

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部