陡河发电厂气力输灰系统改造技术探讨 被引量:1

Analysis on Pneumatic Conveyance Ash System Transformation in Positive Pressure Dense Phase
下载PDF
导出
摘要 大唐国际发电股份有限公司陡河发电厂3号机组1×250 MW发电机组电除尘器于1997年9月投产,并在2007年6月改造为正压浓相气力输灰系统,投入后出现诸多问题,严重影响机组的安全稳定运行。2007年至2012年对3号炉气力输灰系统进行多次技术改造,效果不是很好。2012年利用电除尘增容改造的契机,对3号炉气力输灰系统仓泵配置、仓泵流化系统、管道配置等进行了全面改造。文章针对气力输灰系统在该厂改造前后的设计、运行进行阐述和对比分析,3号炉气力输灰系统改造后运行稳定,对其他电厂气力输灰系统改造有一定的借鉴作用。 The electrostatic precipitator in Datang International Power Generation Co. Ltd. Douhe Power Plant 1 × 250 MW unit was put into operation in September 1997,and in June 2007 the positive pressure dense phase pneu- matic ash conveying system was selected in the transformation. Since the system was put into use, there were still many problems. From 2007 to 2012 several technical improvement were carried out for pneumatic ash conveying sys- tem, but the effect was not very good. To take the opportunity of capacity increment modification for electrostatic pre- cipitator, overall transformation of pneumatic ash conveying system was performed in No3 boiler,including pump con- figuration, pump flow system, pipeline configuration. This paper described and compared the design and operation of pneumatic ash conveying system before and after transformation. Result shows the operation of the system after recon- struction is steady, at the same time, this paper also has something for reference for other power plant in implementing transformation of pneumatic ash conveying system.
作者 赵军才
出处 《华北电力技术》 CAS 2014年第4期67-70,共4页 North China Electric Power
关键词 电厂 除尘器 浓相 气力输灰 power plant electrostatic precipitator dense phase pneumatic ash conveying
  • 相关文献

参考文献2

  • 1GB13223-201l,火电厂大气污染物排放标准[S].
  • 2高香林.燃煤电厂电除尘器.华北电力大学学报,1993.

共引文献59

同被引文献1

  • 1袁礼,江兴涛,潘仁湖,等.一种气力输送系统的输送控制方法[P].中国专利:201110112632.3.2011-07-27.

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部