某斜坡式防波堤工程优化设计 被引量:6

Optimization design of rubble mound breakwater engineering
下载PDF
导出
摘要 在水深较大的海域,传统的斜坡式防波堤结构形式因其断面较大使得造价大幅上升。研究成果和工程实例表明:带减压倒L型胸墙的斜坡堤可以优化传统防波堤设计形式,在保证工程安全性和满足使用要求的同时,可以较好地降低工程造价。结合工程案例,对斜坡式防波堤结构优化设计进行研究和探讨,供类似工程参考。 Traditional mound breakwater structure in deeper waters brings cost rise sharply due to its large cross section. According to some research and engineering examples, It is known that rubble mound breakwater with pressure-relieving inverted-L breast wall can optimize the traditional breakwater pattern, guarantee the safety and meet the using requirements. Meanwhile, it can reduce the cost. Combining with an engineering case, this paper probes into the mound breakwater structure optimization design, which provides reference for similar projects.
出处 《水运工程》 北大核心 2014年第4期57-62,共6页 Port & Waterway Engineering
关键词 防波堤 带减压倒L型胸墙的斜坡堤 优化设计 breakwater rubble mound breakwater with pressure-relieving inverted-L breast wall optimization design
  • 相关文献

参考文献4

二级参考文献3

共引文献38

同被引文献36

  • 1王永学,王国玉.近岸浮式防波堤结构的研究进展与工程应用[J].中国造船,2002,43(z1):314-321. 被引量:39
  • 2丁宁,余建星,侯佳佳.V形浮式防波堤的动压力特性[J].排灌机械工程学报,2014,32(1):29-32. 被引量:5
  • 3劳国昇,冯宏.浮式防波堤性能理论计算[J].海洋工程,1993,11(2):89-97. 被引量:5
  • 4DL5077-1997.水工建筑物荷载设计规范[S].[S].,..
  • 5GB50009-2012,建筑结构荷载规范[S].2012.
  • 6JTSl54-1-2011,防波堤设计与施工规范[S].2011.
  • 7田湾核电5、6号机组取水明渠导流堤断面波浪物理模型试验研究报告[R].大连:大连理工大学,2009.
  • 8田湾核电5、6号机组取水明渠工程波浪整体物理模型试验研究报告[R].南京:南京水利科学研究院,2009.
  • 9JTS1452-2013海港水文规范[S].
  • 10中交天津港湾工程研究院有限公司.中国海监唐山维权执法基地建设项目护岸断面物理模型试验[R].天津:中交天津港湾工程研究院有限公司,2014.