时间窗下单船岸桥调度——基于数学规划和规则的启发式算法 被引量:5

Shore-mounted gantry crane scheduling for single vessel under time window——using mathematical programming and rule heuristic algorithm
下载PDF
导出
摘要 在考虑任务属性中的任务优先顺序和不可同时执行要求,岸桥属性中的岸桥时间窗、转移时间、初始位置、安全距离和装卸速度等因素下,以单艘船舶的最短岸桥作业时间为目标函数,建立单艘船舶岸桥调度的混合整数线性模型P1。计算数据采集于宁波某集装箱港口,通过简化模型P2求解岸桥调度模型P1的下限边界值和排程数据,在此基础上,运用基于规则的启发式算法求解模型P1的岸桥调度时序表。计算结果表示本组合算法能较好地得到满意解,而且比较符合港口实际。 Considering task priority and impossible parallel execution in task attribute and time window, shore-mounted gantry crane or Quay Crane(QC)transfer time, QC initial position, QC’s safe separation distance and loading and unloading velocity in QC attributes, this paper establishes QC scheduling MILP model P1 with the objective of the shortest operation time, and the solution is gotten based on the data from a container terminal in Ningbo, China. In order to get more practical solution, this paper sets up a simplified model P2 to get the lower limit of P1. The rule based heuristic algorithm is used to solve P1. The result states this combination method can be used to get the optimal and more practical solution.
出处 《计算机工程与应用》 CSCD 2014年第9期242-248,263,共8页 Computer Engineering and Applications
基金 上海市自然科学基金创新行动计划(No.10190502500) 上海市教委重点学科(No.J50604) 上海市科委工程中心项目(No.09DZ2250400)
关键词 岸桥指派 岸桥排程 启发式算法 港口运作优化 shore-mounted gantry crane or Quay Crane(QC)assignment QC scheduling heuristic algorithm port oper-ation optimization
  • 相关文献

参考文献1

二级参考文献15

  • 1Port of hamburger, http://www.hafen-hamburg.de/content/ view/31/33/lang,en/, 2008.
  • 2Stahlbock R, Vof3 S. Operations research at container terminals: A literature update. OR Spectrum, 2008, 30: 1-52.
  • 3Ng W C. Crane scheduling in container yards with inter-crane interference. European Journal of Operational Research, 2005, 164: 64-78.
  • 4Daganzo C F. The crane scheduling problem. Transportation Research, 1989, 23B(3): 159-175.
  • 5Peterkofsky R I, Daganzo C F. A branch and bound solution method for the crane scheduling problem. Transportation Research, 1990, 24B(3): 159-172.
  • 6Kim K H, Park Y M. A crane scheduling method for port container terminals. European Journal of Operational Research, 2004, 156: 752-768.
  • 7Vis I F A, de Koster R M B M, Savelsbergh M W E Minimum vehicle fleet size under time-window constraints at a container terminal. Transportation Science, 2005, 39(2): 249-260.
  • 8Bish E K, Chen F Y, Leong Y T, et al. Dispatching vehicles in a mega container terminal. OR Spectrum, 2005, 27: 491-506.
  • 9Kim K H, Bae J W. A look-ahead dispatching method for automated guided vehicles in automated port container terminals. Transportation Science, 2004, 38(2): 224-234.
  • 10Ng W C, Mak K L, Zhang Y X. Scheduling trucks in container terminals using a genetic algorithm. Engineering Optimization, 2007, 39(1): 33-47.

共引文献30

同被引文献23

引证文献5

二级引证文献16

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部