红毛洞电站装机2×10MW工程指标相对并不优,因此设计时要尽量优化减少投资是非常必要的。为此,根据水轮机选择原则并结合目前水轮机的发展情况,对红毛洞电站进行优化选择设计。如通过机型选择比较,推荐HLA551C-LJ-172机型,根据水轮机计算的有关参数,选定2台10 MW悬式水轮发电机等。
Hongmaodong hydropower station has installed plant 2 × 10MW,its engineering index relative are not excellent,therefore it is necessary to optimize the design so as to reduce the investment. Based on the principles for turbine selection and combined with turbine development situation,optimum design is conducted for Hongmaodong hydropower station. For example through type selection,HLA551C-LJ-172 models are recommended; according to the turbine parameters calculation,210 MW suspension hydraulic generator is selected etc.
出处
《黑龙江水利科技》
2014年第2期39-41,共3页
Heilongjiang Hydraulic Science and Technology
关键词
水轮机
模型综合特性曲线
运转特性曲线
调保计算
优选设计
turbine
model synthetic characteristic curve
operating characteristic curve
regulation guarantee calculation