立足于市政水泥混凝土道路加铺沥青面层施工质量的监控,围绕施工的主要工序,对该技术进行探讨。施工过程要做好路面病害处治、应力层设计和面层结构及材料选用方面工作,提高沥青加铺面层的性能和防止反射裂缝的形成,使沥青加铺面层符合设计标准,发挥其功能。
Based on the supervisory control of the construction quality and the main working procedures of repaving the asphalt surface on the municipal cement concrete road,this paper explores and discusses its techniques.This paper stresses the repair and maintenance of the pipeline along the road before construction and focuses on the following three aspects of work during construction:the pavement disease treatment,the stress absorbing layer and the surface layer structure design and materials selection,in order to improve the performance of asphalt overlay and prevent the formation of reflective crack,which make the asphalt overlay meet the design standards and play its part well.
出处
《交通科技与经济》
2014年第2期99-101,共3页
Technology & Economy in Areas of Communications
关键词
道路升级改造
加铺沥青面层
反射裂缝
应力吸收层
road upgrading and reconstruction
repaving the asphalt surface
reflective crack
stress absorbing layer