摘要
针对预应力混凝土连续刚构桥线形控制时存在的实际结构状态与理论计算的偏差问题,提出一种结合参数识别调整、前期预测及偏离分配计算出施工预拱度调整值,并对未浇筑主梁的立模标高进行修正的方法,实践证明采用该方法可避免后续梁段的误差累计,具有广泛推广应用的价值。
In light of the deviation of actual structural condition and theoretical calculation of prestressed continuous concrete steel bridge in the linear control,the paper puts forward a new construction pre-arch adjustment value by combining parameter identification adjustment,preliminary prediction and deviation distribution,and carries out the correction for vertical beam model height without being casted. Practice proves that:ap-plying this method can avoid continuous beam error accumulation. Thus,it is worth promoting.
出处
《山西建筑》
2014年第17期194-195,共2页
Shanxi Architecture
关键词
悬臂梁桥
施工监控
预拱度
调整值
cantilever beam bridge
construction monitoring
pre-arch
adjusted-value