摘要
介绍了桃源水电站厂房设计过程中遇到的一些问题,如结构分缝、进水口和尾水门机轨道梁、主副厂房、厂区集水井及前流道里衬的设计等。为减少工程投资、降低施工难度、节约工期,结合现场实际施工情况,在保证结构安全的前提下,针对这些存在的问题进行了优化设计,确保了厂房建设的工程质量与施工进度。
The problems in the design of powerhouse of Taoyuan Hydropower Station are introduced, including structure joints, rail beams of gantry cranes in intake and tailwater, main and auxiliary powerhouses, water collection well of powerhouse and front flow channel lining. To reduce investment, construction difficulty and construction duration, some designs are optimized to solve above problems after considering the actual construction conditions and on the basis of structure safety can be ensured. These optimizations ensure the quality and progress of powerhouse construction.
出处
《水力发电》
北大核心
2014年第6期35-38,共4页
Water Power
关键词
厂房设计
施工分缝
门机轨道梁
主厂房
副厂房
桃源水电站
powerhouse design
construction joint
gantry crane rail beam
main powerhouse
auxiliary powerhouse
TaoyuanHydropower Station